51 Melcher

Location:  Boston, MA

Market:  Commercial

General Contractor:  Wise Construction

Timeline:  Spring 2023 – 2024

Services Provided: 

  • HVAC
  • Mechanical
  • Fabrication

Project Overview

CMNE recently completed an HVAC core/shell project for a 100,000 sf, nine-story building in Boston. HVAC equipment was furnished and installed along with relevant piping, much of which was fabricated.

The equipment included:
• 9 Air Handler Units (AHUs)
• 1 Glycol Recovery Skid with 4 Air Source Heat Pumps
• 2 Energy Recovery Units (ERVs) with Glycol Recovery Coils
• 9 Pumps (Chilled Water, Hot Water, and Dual Temp Water)
• 2 Boilers